Improvement of Power Generation Facility Investment Systems for Achieving Resource Adequacy in Electric Power Industry - KDI 한국개발연구원 - 연구 - 보고서
본문 바로가기

KDI 한국개발연구원

KDI 한국개발연구원

SITEMAP

KDI 정책포럼 Improvement of Power Generation Facility Investment Systems for Achieving Resource Adequacy in Electric Power Industry 2015.01.29

표지

Series No. Vol. 260 (eng.)

KDI 정책포럼 Improvement of Power Generation Facility Investment Systems for Achieving Resource Adequacy in Electric Power Industry #시장규제: 진입, 가격, 품질규제 #환경 및 에너지

2015.01.29

  • 프로필
    이수일 겸임연구위원
영문요약
□ Investment in power generation facilities in Korea is planned and implemented in accordance with the Basic Plan on Electricity Demand and Supply, which involves the following problems:

- Problem 1: An underestimation of long-term electricity demand due to optimistic projections on electricity price results in insufficient investment in power generation facilities.

- Problem 2: Uncoordinated investment plans in power generation facilities and transmission networks can exacerbate regional disproportion of power facility distribution and can cause inefficiency and instability in transmission networks.

- Problem 3: Leaving the assessment of uncertainty factors up to the small group who lead the planning may distort future power generation mix.

- Problem 4: A considerable number of the planned investment projects remain unexecuted due to the absence of effective means to enforce or induce implementation of investment plans


□ This paper attempts to propose deregulation of power generation market entry and introduction of a capacity obligation scheme as measures to deal with Problems 3 and 4.

- The efforts to handle Problems 1 and 2 is not addressed in this paper, as there were efforts to resolve these concerns in the Sixth Basic Plan on Electricity Demand and Supply in 2012.

- Uncertainty factors affecting the economic feasibility and environmental performance of power generation facilities vary by energy source. In the case of coal- and LNG-fired power generation, the possibility for distortion within the power generation mix can be minimized by lowering the barriers to market entry. This can be achieved by offering more autonomy to power producers in assessing future uncertainty factors.

- Uncertainties over investment in power generation facilities can be minimized via a contract between power producers and suppliers, arranged through the introduction of a capacity obligation scheme. In such a scheme, obligation is imposed upon the power supplier (KEPCO in Korea) to secure power capacity that can ensure a stable supply to meet future demand for electricity.
목차
1. Introduction

2. Current State and Problems of Systems Related to Power Generation Facility Investment

3. Measures to Improve Power Generation Facility Investment Systems for Achieving Optimal Power Generation Mix in Electric Power Industry
관련 자료 ( 9 )
  • 주요 관련자료
  • 같은 주제자료
공공누리

한국개발연구원의 본 저작물은 “공공누리 제3유형 : 출처표시 + 변경금지” 조건에 따라 이용할 수 있습니다. 저작권정책 참조

담당자
윤정애 전문연구원yoon0511@kdi.re.kr 044-550-4450
이 페이지에서 제공하는 정보에 대하여 만족하시나요?
네이버로그인
카카오로그인
보안문자 확인

무단등록 및 수집 방지를 위해 아래 보안문자를 입력해 주세요.

KDI 직원 정보 확인

담당자 정보를 확인해 주세요.

등록완료

소중한 의견 감사드립니다.

등록실패

잠시 후 다시 시도해주세요.

Join our Newsletter

매일 새로운 소식으로 준비된 KDI 뉴스레터와 함께
다양한 정보를 확인하세요.