KDI 정책포럼 Analysis and Implications of the Determinants of CIRR for the Seamless Execution of PPP Projects

표지

Series No. No. 276 (2020-01), eng.

KDI 정책포럼 Analysis and Implications of the Determinants of CIRR for the Seamless Execution of PPP Projects #SOC #민간투자사업평가(적격성조사, 타당성분석, 협상보고서, 자금재조달) #교통 및 물류

2020.01.21

  • 프로필
    김강수 선임연구위원
영문요약
■ The contracted internal rate of return (CIRR) of Korea's public-private-partnership (PPP) projects does not properly reflect the risks associated with the different types and characteristics of facilities and government support. Rather, the rates are set at the same level as similar preceding projects.

- The characteristics of a project, e.g. facility type, amount of private investment, and operation period, and the ensuing risks are not sufficiently reflected in the decisions over CIRR. Moreover, the construction subsidy―a government risk-sharing and support policy―inadequately contributes to lowering the rate.

- The project review period and VfM test do not have a meaningful effect on determining the CIRR, implying that project evaluations and analyses need to be improved.

■ For the seamless execution and invigoration of PPP projects and lower user fees, the CIRR must be fixed at an appropriate level through more active negotiations and efforts in addition to taking the CIRR of similar existing PPP projects into account.

- A significantly low CIRR relative to the risks could diminish the incentive to privately invest or could even lead to the bankruptcy of an ongoing project. On the other hand, an excessively high rate could raise the user fee or necessitate larger government subsidies.

- To determine the suitable CIRR, the risks and effects of government support must be analyzed. In particular, policies that encourage competition in the PPP market must be developed to lower user fees through policies, e.g. transparent disclosure of information, simplified implementation procedures, increased provision of guarantees, and the provision of compensation for the cost of failed proposals, etc.
목차
1. Issues

2. Status of the CIRR of PPP Projects

3. Analysis of the Determinants of CIRR

4. Conclusion and Policy Suggestions
동일 주제 자료 ( 10 )
  • 주요 관련자료
공공누리

한국개발연구원의 본 저작물은 “공공누리 제3유형 : 출처표시 + 변경금지” 조건에 따라 이용할 수 있습니다. 저작권정책 참조

담당자
윤정애 전문연구원yoon0511@kdi.re.kr 044-550-4450
이 페이지에서 제공하는 정보에 대하여 만족하시나요?
네이버로그인
카카오로그인
보안문자 확인

무단등록 및 수집 방지를 위해 아래 보안문자를 입력해 주세요.

KDI 직원 정보 확인

담당자 정보를 확인해 주세요.

등록완료

소중한 의견 감사드립니다.

등록실패

잠시 후 다시 시도해주세요.

Join our Newsletter

매일 새로운 소식으로 준비된 KDI 뉴스레터와 함께
다양한 정보를 확인하세요.